(Yuba-Sutter, CA) – PG&E is adjusting its gas line upgrade schedule for Marysville.
Originally scheduled to begin next Monday (2/26), it will instead begin Monday, March 11th. All new pipes, and in some cases, gas meter upgrades, will be done along 9th Street, between F and G, H and I, along H between 8th and 10th, along I between 8th and 9th, along J between 6th and 8th, and 6th Street between J and Olive.
Work is expected to continue until May according to a press release, as crews bore and trench to replace approximately 3,800 feet of gas line serving 56 business and residential customers.